Scope
1.3
Updated
16 November 2026
Progress
from the status alone

as at 16 November 2026

Scope. A programme-owned development project; the vendor’s demo project for reference.

Achieved.

  • 16 Nov: the demo storefront is connected to commercetools and pulls product, price and inventory from it (Pat).
  • 3 Nov: the vendor demo project is open; the programme project is to provision.