Skip to content

3 · Build the POC

9 November to the demo on 18 December; the store leg 18 to 29 January as at 16 November 2026

16%

The build proves data moving across the systems in one flow, on synthetic data, in eight steps: the catalogue load, the storefront, cart and checkout, the order event and the order engine, the pick-and-pack app, the loyalty earn, the POS adapter mock, and one trace through every step. Where a step names a domain service, the POC runs its mock unless the stand-in register shows it built. Around the flow sit the services in Azure (built from Bicep in the sandbox), CI/CD on GitHub Actions, the commerce engine model tests, Porters as the second skin, and the teardown-and-rebuild run that proves nothing in the sandbox is hand-made.

The build order. 9 to 20 November: the repositories and the pipeline, the gateways and the first Container App from Bicep, the storefront shell with sign-in, the catalogue load (gate: product pages served from commercetools through the Experience API to a signed-in shopper). 23 November to 11 December: search, cart, checkout on the CyberSource sandbox, order capture, the order event with the order engine and loyalty mocks, the second skin, the model tests (gate: a paid order in commercetools and a balance that moved). 14 to 18 December: the teardown-and-rebuild run, the acceptance record, the stand-in register (gate: the demo on 18 December). 18 to 29 January, after the trading peak: the pick-and-pack app on a phone, the POS adapter mock, the read-out with the measured baseline.

The last four items were added on 16 November from Pat’s next steps.

ItemStatusProgressOwnerDueMoved
Step 1 · Catalogue load into commercetools and Coveo In progress Moved this week
50%
Pat 20 Nov 16 Nov
Step 2 · Thirsty Camel storefront on the Experience API In progress Moved this week
50%
Pat 20 Nov 16 Nov
Step 3 · Cart and checkout with CyberSource In progress Moved this week
50%
Pat 11 Dec 16 Nov
Step 4 · Order event, order engine, Store Operation API Not started
0%
Pat 11 Dec 3 Nov
Step 5 · Pick-and-pack app on a phone In progress Moved this week
50%
Pat 29 Jan 16 Nov
Step 6 · Loyalty earn through the loyalty contract Not started
0%
Pat 11 Dec 3 Nov
Step 7 · POS adapter mock, store-initiated pull Not started
0%
Pat 29 Jan 3 Nov
Step 8 · One trace in Application Insights Not started
0%
Pat 18 Dec 3 Nov
The Experience API on Container Apps in the sandbox In progress Moved this week
50%
Pat 20 Nov 16 Nov
Sandbox services from Bicep Not started
0%
Pat 20 Nov 3 Nov
CI/CD on GitHub Actions Not started
0%
Pat 20 Nov 3 Nov
Payment adapter, thin, to the CyberSource sandbox Not started Moved this week
0%
Pat 11 Dec 16 Nov
Porters as the second skin Not started
0%
Pat 11 Dec 3 Nov
Commerce engine model tests Not started
0%
Sean 11 Dec 3 Nov
Teardown-and-rebuild run and the acceptance record Not started
0%
Pat 18 Dec 3 Nov
Staff access management Not started Moved this week
0%
Pat, with DW none set 16 Nov
Store pick device enrolment Not started Moved this week
0%
Pat, with Henri none set 16 Nov
Mobile app lifecycle management In progress Moved this week
50%
Pat, with Henri none set 16 Nov
Geo-polygon mapping and delivery boundaries Not started Moved this week
0%
Pat, with Henri none set 16 Nov
  • The order runs through all eight steps on the demo day with no manual step, and one trace follows it.
  • Every resource in the sandbox resource group is destroyed and recreated from Bicep by the pipeline, and the storefront redeploys, with no manual step.
  • Every stand-in is listed with the contract it implements and the component that replaces it.
  • The model tests are marked passed, failed, blocked or not tested, with their evidence.