3 · Build the POC
The build proves data moving across the systems in one flow, on synthetic data, in eight steps: the catalogue load, the storefront, cart and checkout, the order event and the order engine, the pick-and-pack app, the loyalty earn, the POS adapter mock, and one trace through every step. Where a step names a domain service, the POC runs its mock unless the stand-in register shows it built. Around the flow sit the services in Azure (built from Bicep in the sandbox), CI/CD on GitHub Actions, the commerce engine model tests, Porters as the second skin, and the teardown-and-rebuild run that proves nothing in the sandbox is hand-made.
The build order. 9 to 20 November: the repositories and the pipeline, the gateways and the first Container App from Bicep, the storefront shell with sign-in, the catalogue load (gate: product pages served from commercetools through the Experience API to a signed-in shopper). 23 November to 11 December: search, cart, checkout on the CyberSource sandbox, order capture, the order event with the order engine and loyalty mocks, the second skin, the model tests (gate: a paid order in commercetools and a balance that moved). 14 to 18 December: the teardown-and-rebuild run, the acceptance record, the stand-in register (gate: the demo on 18 December). 18 to 29 January, after the trading peak: the pick-and-pack app on a phone, the POS adapter mock, the read-out with the measured baseline.
The last four items were added on 16 November from Pat’s next steps.
| Item | Status | Progress | Owner | Due | Moved |
|---|---|---|---|---|---|
| Step 1 · Catalogue load into commercetools and Coveo | In progress Moved this week | Pat | 20 Nov | 16 Nov | |
| Step 2 · Thirsty Camel storefront on the Experience API | In progress Moved this week | Pat | 20 Nov | 16 Nov | |
| Step 3 · Cart and checkout with CyberSource | In progress Moved this week | Pat | 11 Dec | 16 Nov | |
| Step 4 · Order event, order engine, Store Operation API | Not started | Pat | 11 Dec | 3 Nov | |
| Step 5 · Pick-and-pack app on a phone | In progress Moved this week | Pat | 29 Jan | 16 Nov | |
| Step 6 · Loyalty earn through the loyalty contract | Not started | Pat | 11 Dec | 3 Nov | |
| Step 7 · POS adapter mock, store-initiated pull | Not started | Pat | 29 Jan | 3 Nov | |
| Step 8 · One trace in Application Insights | Not started | Pat | 18 Dec | 3 Nov | |
| The Experience API on Container Apps in the sandbox | In progress Moved this week | Pat | 20 Nov | 16 Nov | |
| Sandbox services from Bicep | Not started | Pat | 20 Nov | 3 Nov | |
| CI/CD on GitHub Actions | Not started | Pat | 20 Nov | 3 Nov | |
| Payment adapter, thin, to the CyberSource sandbox | Not started Moved this week | Pat | 11 Dec | 16 Nov | |
| Porters as the second skin | Not started | Pat | 11 Dec | 3 Nov | |
| Commerce engine model tests | Not started | Sean | 11 Dec | 3 Nov | |
| Teardown-and-rebuild run and the acceptance record | Not started | Pat | 18 Dec | 3 Nov | |
| Staff access management | Not started Moved this week | Pat, with DW | none set | 16 Nov | |
| Store pick device enrolment | Not started Moved this week | Pat, with Henri | none set | 16 Nov | |
| Mobile app lifecycle management | In progress Moved this week | Pat, with Henri | none set | 16 Nov | |
| Geo-polygon mapping and delivery boundaries | Not started Moved this week | Pat, with Henri | none set | 16 Nov |
Part 3 closes when
Section titled “Part 3 closes when”- The order runs through all eight steps on the demo day with no manual step, and one trace follows it.
- Every resource in the sandbox resource group is destroyed and recreated from Bicep by the pipeline, and the storefront redeploys, with no manual step.
- Every stand-in is listed with the contract it implements and the component that replaces it.
- The model tests are marked passed, failed, blocked or not tested, with their evidence.